Projects
 
 
 
Primary School Sience (2)

 

 

Account on the process of preparing the primary school mathematics collection

 

 

Script

 Before script writing started, the subjects and titles were determined in 6 sessions. The scientific experts provided each part’s scientific subjects according to the results and gave them to the script writer. Each program’ script was 2 to 4 times rewritten by the script writer. This process started in December, 2002 and ended in March 2002.

 

Story board

Each episode's script was analyzed by the director, the graphist and the animator. So a separate story board was prepared for each of them, in which the movements and their times, and each program’s graphical texture was carefully defined. This process started in March, 2002 and finished in April, 2002.

 Scheduling

As the project budget was provided in the last days of the Iranian year and the coming vacations, executing the three and two-dimensional animations, the graphical ideas and the mixed plans was scheduled to start on March 26th and end on June, 26th. There was a schedule for each week according to the number of programs and plans, and at the end of the week the progress would be compared with the schedule. The project time was short and it made working difficult, so 12 hours of daily work was needed, which sometimes included the holydays.

 

Animation making

Before starting to make the program's plans, a new cover was made for the animation characters in order to give them more movement capabilities. In the last series the time of saying the words and sentences was fixed when forming the animation characters, lips according to the script. In this method the speech and the movements of the lips didn’t exactly match, and a lot of time was wasted trying to match them. In the new series besides speech scheduling, the whole script was once recorded by computer and the lips, movements were done according to the sounds when designing the movements. Though it took a lot more time, the result was great. The grouped tried their best to have variety in the animations in spite of lack of time. So a separate setting and graphic method was designed for each program and none of the movements or models were repeated, and we tried to have one or two film-animation mixed plans in each part. This was also done simultaneously with the other activities since March till July.

 

Film shooting

 It started since December when the general idea of the script was known. The needed scenes were taken as the group traveled to different part of Iran for other projects. This process finished in June. The scenes were taken in Karaj, Qazvin,Khomein, Qom, Abadan, Mashad, some northern cities, Haraz, Firoozkooh, Kan, and places like Payam airport, the meteorology centre and ...

 

Archives scenes

The group believed in using new and beautiful plans, and tried their best to have such plans as far as possible, but in some cases when the subject called foe it a few archives plans were used, like the ones of the pole and its animals, sea animals and some plans of galaxys and the solar system.

 

Editing

When each program’s animations were made, they were separately edited and changed if needed. The general editing started in May and finished in July.

 

Sound mixing

As mentioned before, matching the lip movements of the characters with the speech was done quite carefully. The whole script was recorded in 4 sessions and then matched with the movements by computer.

 

Sound editing

The sound editing which had started with editing different parts of the program, completed in this stage.

 

Music

When each program was ready, it was given to the musician. Composing music for all parts of the program took almost one month.

Songs

When the music was being composed, 2 songs were decided to be composed for the beginning and ending of each part. The songs were composed but there was not enough time to perform them with the same quality as the other parts, so they were omitted and the music was used for the beginning and ending.

 

Mixing

When the music was ready, the whole project was mixed in 4 days.

Final evaluating

As the scientific experts’ ideas were carefully regarded in writting the script and making the programs, and one of the experts was present at film shootings, and also there was a close cooperation between the group and the experts when making the animations, this process was done in a short time with no big problem. Each part was checked by the experts before sound mixing and the whole project was observed again after the technical process. There were only a few points which were taken care of easily, and the 13 episodes were handed in August, 2003.